Five Whys vs Fishbone Diagram

Five Whys vs Fishbone Diagram

Both techniques get taught in the same hour and used interchangeably, which is unfortunate, because they make opposite assumptions about the problem in front of you. One assumes there is a chain to follow. The other assumes you do not yet know where to look.

Section 5 of the PMBOK® Guide Eighth Edition includes both among the analytical techniques a team can use, and the selection is straightforward once you ask what you already know about the problem.

What each technique assumes

Five whys assumes a single causal chain. You start at the effect and ask why repeatedly, each answer becoming the next question, until you reach something worth acting on. It is quick, it needs no preparation, and it works well where the chain genuinely is linear and the people answering know the territory. Its weakness is structural: a chain has one branch at each step, so a problem with four contributing causes produces a tidy answer covering one of them, and the tidiness is persuasive.

A fishbone spreads outwards. The effect goes at the head and possible contributing causes are gathered under categories, so the group is prompted to look in places it would not have chosen: people, method, equipment, materials, environment, measurement, or whatever set suits the domain. It takes longer, it needs a group and somebody to facilitate, and it produces hypotheses rather than answers. Nothing on a fishbone is proved by being on it.

Choosing by what you already know

Where the chain is obvious, follow it. A single failure with a clear sequence and people in the room who know the system: five whys will get there in fifteen minutes and a fishbone would be ceremony.

Where the cause is genuinely unknown, spread out first. Recurring problems, intermittent faults and anything that has already survived one investigation deserve the wider sweep, because the reason they persist is usually that the obvious chain was followed and fixed already.

Where the question is contested, start wide on purpose. When two groups each believe the other’s area is at fault, five whys becomes a negotiation about which first answer to accept. A fishbone puts every area on the same board, including both of theirs, which changes the conversation from blame to evidence and is worth the extra half hour for that reason alone.

An instrument that stopped four times a term

A university research facility had a recurring problem with one analytical instrument: it dropped out of calibration and needed a service visit roughly four times a term, against perhaps once a year for the same model elsewhere on campus.

Two investigations had already been done, both with five whys, both by capable people. The first had concluded that the calibration procedure was being run incorrectly by newer users and had produced a training session. The second had concluded that the consumables were being stored too long and had tightened the ordering. Both findings were true and neither had changed the failure rate.

The third attempt used a fishbone, in a room with the laboratory manager, two users, the estates engineer and the supplier’s field technician. It produced about twenty candidate causes across the categories, most of which were wrong, and three that nobody had previously connected: a daisy-chained extension lead feeding the bench from a socket on the far wall, a stack of sample boxes that had been pushed against the wall vent in the summer, and a door to the corridor that was propped open during busy periods.

Testing those took a fortnight. The extension lead mattered a little. The vent and the door mattered a great deal, because between them they had moved the room’s temperature stability outside the instrument’s specification during exactly the periods when it was most used.

With the area narrowed, five whys then did its job properly on the vent: why were the boxes there, because the store was full, why was the store full, because a second research group had been moved into the building without additional storage, which was a decision taken elsewhere and fixable in a way that no amount of instrument training would have been.

Running either one well

Ask for evidence at each step. Every answer in a five whys chain, and every cause promoted off a fishbone, should be something somebody can show. Without that discipline both techniques produce a chain of plausible assertions, which is more dangerous than no analysis at all because it comes with a diagram attached.

Stop at something you can act on and control. Continuing until the answer is organisational culture or inadequate funding produces a true statement and no action. The right stopping point is the last cause somebody in the building can change, with the rest recorded and passed to whoever can.

For a PMP® candidate, what helps is seeing that the techniques assume different problem shapes, so a scenario about a recurring fault that has already been investigated is pointing towards the wider sweep. A response that runs another causal chain repeats the method that has already failed twice. Situations where the analysis was competent and aimed at one branch of a multi-cause problem get proper time in a structured PMP exam preparation course.

On a live project, take a problem that has come back more than once and check what technique was used the last time. If it was a causal chain, half an hour with a group and a wider sweep will usually surface something nobody thought to ask about, and the candidates it produces can then be tested one at a time.

By Andre Malowney

Interested in going further?

A tidy answer to a messy problem is the most convincing thing an investigation can produce and the hardest to argue with. Omega’s PMP® Exam Preparation works through analysis techniques and the assumptions each one carries.

Free study planner

Find out how ready you are for the PMP® exam

Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.

Want to prepare with a trainer? See our five-day live online PMP® course.

Both techniques appear among the analytical methods in the PMBOK® Guide Eighth Edition.

Ad · Amazon affiliate link.

References

A176: Root Cause Analysis in Projects: How to Fix Causes, Not Symptoms
A181: Affinity Diagrams: Turning Messy Ideas Into Structure
A118: Burn-up vs Burn-down Charts
A180: Facilitation Techniques for Difficult Project Conversations
A148: Which Conflict Resolution Technique Should You Use?

PMP and PMBOK are registered marks of the Project Management Institute, Inc.

Flyer for Enlighten Publications inviting readers to join their Early Reader List for access to nonfiction on psychology, work, culture, technology, and modern life. Features a QR code to scan, website URL enlighten-publications.com/early-reader-list, and a man reading a book.