Matrix, Functional or Projectised? How Structure Changes the PM’s Job

Matrix, Functional or Projectised? How Structure Changes the PM’s Job

The words are taught as a taxonomy and used as an excuse. A project manager says the organisation is a weak matrix, everyone nods, and nothing about how the project is run changes. The categories are worth knowing because they predict specific difficulties, and the more useful skill is reading which one you are actually in, because the chart frequently says one thing and the behaviour says another.

Section 2.2.5 of The Standard for Project Management sets out the structures projects operate within, and the practical translation is about where three particular kinds of power sit.

What the chart does not tell you

Reporting lines describe who is formally accountable for a person’s employment. They say nothing about whose work that person does on a Tuesday, which is decided by whoever has been most persuasive, most urgent or most senior in the preceding week.

The behaviour is readable from three questions. Who decides what this person works on when two demands collide? Who writes their appraisal and influences their progression? Who holds the money that pays for their time? Where all three answers are the functional manager, the project manager is working by influence whatever the chart claims. Where all three are the project manager, the authority is real. Most organisations sit somewhere in between, and knowing precisely where is the difference between a workable plan and an optimistic one.

The three arrangements and what each costs

Functional. People sit in departments, the department head sets priorities, and project work competes with operational work continuously. The project manager’s authority is persuasive, the role is often part-time, and the characteristic failure is that project work is done in the gaps. What works here is early agreement with the department head, who controls the answer, small and visible commitments, and a plan whose float absorbs the weeks when operations wins.

Matrix. Authority is genuinely shared, and the interesting variable is which way the balance tips. In a weak matrix the functional side holds priority and appraisal; in a strong one the project side holds both and the functional manager retains professional standards and career development. Most organisations describe themselves as balanced, which usually means nobody has decided, and the cost lands on whoever is being pulled two ways, which is the team member rather than either manager. The valuable move is making the split explicit for the specific people involved: this person, this proportion, priority decided by this person when it collides.

Projectised. The project manager holds the people, the budget and the priority, and delivery gets markedly easier. The difficulties move to new places: professional standards drift without a functional home, people worry about where they go when the project ends, and the organisation can find itself with five projects each holding a specialist who is fully occupied on one and needed by three.

A shutdown run across two reporting lines

An oil terminal ran a major shutdown every four years. The shutdown project manager held the budget and the programme, and every person working the shutdown reported day to day to a terminal operations line that continued to run the site.

On paper it was a strong matrix. In practice, the operations manager set priorities whenever a live plant issue arose, which was several times a week, and she was right to: the terminal was still moving product and safety sat with her. The shutdown plan had been built on the assumption of uninterrupted crews and it was wrong from the second week.

What resolved it was not an escalation about authority. It was a rule agreed between the two of them in front of their sponsor, and it took twenty minutes. Anything affecting live plant integrity took the operations manager’s priority without discussion. Anything else stayed with the shutdown until the two of them agreed otherwise, and any diversion lasting more than half a shift was logged and its effect on the critical path shown at the next morning’s meeting.

The logging is what changed behaviour. Within a fortnight it was visible that about nine per cent of the shutdown’s labour was going to live plant work, most of it genuinely necessary and some of it not. The genuinely necessary portion was added to the plan as an allowance, which made the programme honest. The rest stopped, because nobody wanted their name against a diversion that had cost two days on the critical path for something that could have waited a week.

Working with the structure you have

Agree the priority rule before you need it. Every shared-authority arrangement needs a stated answer to what happens when two demands collide, agreed by both managers, in front of whoever they both report to. Agreed in advance it takes twenty minutes. Agreed during a collision it takes a week and leaves residue.

Make the cost of the structure visible. Where priority conflicts are consuming the project, the useful response is a number rather than a complaint: this many hours, this effect on the date. Organisations tolerate a structural cost indefinitely while it is invisible and act on it quickly once it has a figure attached.

For a PMP® candidate, what matters is that structure determines the authority a project manager actually holds, so a scenario where a team member is being pulled between two demands is describing a priority rule that does not exist. A response that instructs the person has used authority the project manager may not have. A structured PMP exam preparation course examines situations where the plan assumes an authority the structure does not provide.

Answer the three questions about the two people you most depend on. Who decides their priorities, who writes their appraisal, who pays for their time. If the answer to any of them is somebody you have not spoken to in the last month, that is the conversation with the highest return available to you this week.

By Andre Malowney

Interested in going further?

Knowing precisely how much authority you hold, and building a plan that does not quietly assume more, is one of the least glamorous skills in delivery. Omega’s PMP® Exam Preparation works through delivery inside structures that share authority.

Free study planner

Find out how ready you are for the PMP® exam

Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.

Want to prepare with a trainer? See our five-day live online PMP® course.

Organisational structures and their effect on projects are covered in The Standard, published with the PMBOK® Guide Eighth Edition.

Ad · Amazon affiliate link.

References

A019: Why Organisational Knowledge Repositories Matter
A007: The Standard for Project Management vs the PMBOK Guide
A026: How Project Managers Provide Organisational Insight
A017: Organisational Process Assets: What They Actually Include
A091: Project Governance vs Organisational Governance: What’s the Difference?

PMP and PMBOK are registered marks of the Project Management Institute, Inc.

Flyer for Enlighten Publications inviting readers to join their Early Reader List for access to nonfiction on psychology, work, culture, technology, and modern life. Features a QR code to scan, website URL enlighten-publications.com/early-reader-list, and a man reading a book.