People Are Resources, But Not Just Resources

People Are Resources, But Not Just Resources

Planning requires counting, and counting requires units, so people appear in plans as fractions of themselves: half an analyst for six weeks, two engineers from March. The language is necessary and nobody has found a better one. It also stops describing anything real at precisely the moment a project gets difficult, which is why plans built entirely in those units fail in ways that look mysterious from the outside.

Section 2.6.1 of the PMBOK® Guide Eighth Edition opens the resource material with concepts covering both people and physical resources, and the practical skill is holding both readings of a person at once: the unit for planning, and the individual for everything else.

What the resource language gets right

It makes capacity visible. Without a common unit there is no way to see that three projects have committed the same person for a hundred and forty per cent of their time, and that arithmetic prevents a great deal of avoidable failure. Anybody who has worked in an organisation that does not do it will defend the practice.

It supports a conversation about trade-offs. A line manager, a portfolio group and a sponsor can discuss allocations because the units are comparable. The conversation is coarse and it is better than the alternative, which is whoever asks most persistently getting the people.

Where it stops working

People are not interchangeable. Two names in the same role band will differ by a factor that no plan records, and on specialist work the difference is not marginal. Replacing a departing engineer with another engineer of the same grade is a valid entry in a resource system and frequently a fiction in the work.

Utilisation is a poor measure of value. A person at ninety-five per cent utilisation has no capacity to absorb anything, so the first problem that arrives displaces something else, and the queueing effect spreads through everything they touch. Organisations that target high utilisation are buying a number and selling responsiveness, and the cost lands in delivery rather than in the metric.

Knowledge concentrates and does not appear in the plan. On most projects there is one person who knows how something actually works, and their unavailability stops more than their share of the work. A resource plan shows them as one unit among several, which is exactly as informative as a plan that shows a sole-source supplier as one line item among many.

A utilisation target and a project room desk

A consultancy ran its delivery teams against a utilisation target of eighty-five per cent chargeable time. The target was reasonable by industry standards and it was measured rigorously.

On a client engagement of about nine months, the effect was visible in the project room. One consultant held the client’s data model in her head, having built it in the first six weeks. Her desk was the only one in the bank that looked worked at: binders open, the model printed and taped along the divider, everything within reach. The others were clear, because their occupants were between client sites, filling the gaps in their own utilisation.

Nothing about that was wrong until she took two weeks of leave she had deferred twice. In those two weeks, three decisions waited, one was taken without her and had to be reversed, and a client workshop was rescheduled at a cost of about eleven thousand pounds in consultant time. The exposure had been visible on the wall of the project room for months.

What the engagement partner changed was small and unpopular at first. Two days a fortnight of a second consultant’s time were made non-chargeable and spent pairing with her on the model, which cost the firm about four days of utilisation across the quarter. By the time she left the engagement, two people could answer the client’s questions, and the transition to the support phase took a week instead of the six the firm normally budgeted.

The utilisation figure for that team dropped by about two points and the engagement’s margin improved, which took some explaining, because the two numbers are reported in different places to different people.

Planning with both readings in view

Plan in units, then read the plan for names. Once the arithmetic works, go through it asking which specific people the plan depends on, and what happens to each dependency if that person is unavailable for a fortnight. The answer is usually one or two names, and they are rarely the most senior.

Leave slack deliberately. A team planned to full capacity will deliver whatever arrives first and defer everything else, which is how unplanned work quietly sets the priorities. Planning to something below full utilisation is not generosity; it is the mechanism that lets a team absorb the ordinary interruptions of a real organisation without reordering itself every week.

For a PMP® candidate, the useful reading is that resource planning needs both the unit and the individual, so a scenario where a competent replacement has not restored progress is describing knowledge that was never held in units. A response that adjusts the allocation has treated two people as equivalent. Situations where the numbers balance and the project is still stuck are among the more instructive ones in a structured PMP exam preparation course.

Name the person whose fortnight of leave would hurt most, and write down what specifically would stop. Then spend a few hours of somebody else’s time this month reducing that list. It is the cheapest risk mitigation available on most projects and it almost never appears in a risk register.

By Andre Malowney

Interested in going further?

Plans are built in units and delivered by individuals, and the gap between those two facts is where a good deal of project management actually happens. Omega’s PMP® Exam Preparation works through resourcing with both readings in view.

Free study planner

Find out how ready you are for the PMP® exam

Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.

Want to prepare with a trainer? See our five-day live online PMP® course.

The concepts behind resource management are introduced in the PMBOK® Guide Eighth Edition.

Ad · Amazon affiliate link.

References

A142: The PMBOK 8 Resources Performance Domain: What It Really Covers
A144: Resource Planning in a World of Shared Teams
A147: Conflict Is Not Always a Problem
A150: Motivation Is Not a One-Size-Fits-All Technique
A111: Dates Are Not a Schedule

PMP and PMBOK are registered marks of the Project Management Institute, Inc.

Flyer for Enlighten Publications inviting readers to join their Early Reader List for access to nonfiction on psychology, work, culture, technology, and modern life. Features a QR code to scan, website URL enlighten-publications.com/early-reader-list, and a man reading a book.