A column of dates on a whiteboard is a perfectly honest thing. It records what people are aiming at, everybody can read it, and on a small piece of work it may be all that is needed. It becomes a problem when it is doing the job of a schedule, because the questions that arrive during delivery are not questions a date can answer.
Section 2.3.1 of the PMBOK® Guide Eighth Edition sets out the concepts behind scheduling, and the practical way to judge any schedule is by what it lets somebody do on the day something changes.
Four properties of a schedule you can use
Logic that holds. Activities linked by genuine relationships, so that moving one moves what depends on it. Without this the document cannot answer a single what-if question, which is most of what a schedule is for.
Durations somebody will stand behind. Numbers from the people who will do the work, with their assumptions recorded. A duration produced by working backwards from a target date is a wish with a number attached, and it will not be met by the people who never agreed to it.
Resources attached where they matter. At least on the activities where a specific team, specialist or piece of plant is required. This is what allows the plan to reveal the week where four people are needed and two exist, which is otherwise discovered in that week.
Maintained by somebody close to the work. Updated on a rhythm, with actual progress, by a person who knows whether an activity is genuinely finished. A schedule maintained remotely from reports drifts from reality steadily and invisibly.
What a useful schedule lets you do
Answer the what-if question. The steel is two weeks late: what moves, what does not, and when does the end date change. This is the question a project manager is asked most often and the one a date list cannot touch.
See where to spend attention. Which forty of four hundred activities govern the outcome this month, and which chains are about to become the ones that matter. Attention is the scarcest thing a project manager has and the schedule is how it gets allocated.
Refuse a request with evidence. Somebody wants an extra scope item inside the same window, and the honest answer is that it costs eleven days on the critical path. That is a conversation about a number rather than about willingness, and it goes considerably better.
Ten thousand activities nobody could maintain
A contractor building a distribution centre produced a programme of about ten thousand activities, properly linked, resource-loaded and impressive at the tender stage. It was a genuine model, and it was accurate on the day it was issued.
Maintaining it needed roughly three days a week of a planner’s time, and the planner was shared with two other projects. Updates fell behind by a fortnight, then by six weeks. By month five the programme in the system no longer matched the site, and everybody knew it, so decisions were being made from the short-term look-ahead the site team produced themselves on a whiteboard by the door: a column of dates, smudged, with nothing beside them.
The rolled programme prints stood banded in the corner of the office. The tender model had become a document nobody consulted, and the project was being run from a list of dates that could not answer any question beyond what somebody was aiming at this week.
The rebuild took a fortnight and produced about nine hundred activities, linked, with the critical chains intact and detail only where it mattered: the sequences with genuine dependency risk. It could be updated in half a day a week, which the planner had, so it was.
The look-ahead whiteboard stayed, because the site team liked it and it was useful at that horizon. The difference was that the dates on it now came out of a model somebody could interrogate.
Getting the level of detail right
Detail costs maintenance. Every activity added is something somebody has to update, and the point at which a schedule exceeds the time available to maintain it is the point at which it starts describing history. Deciding what you can actually keep current is a design decision, not a compromise.
Put the detail where the risk is. Fine granularity on sequences with real dependency exposure or scarce resources, coarser granularity on work that is well understood and self-contained. A uniform level of detail across a whole project is a sign that nobody chose one.
For a PMP® candidate, what helps is seeing that a schedule is a model whose value shows when something changes, so a scenario about a project unable to assess a delay is describing a schedule with no logic or no maintenance. A response that reissues the dates leaves the project in the same position next month. A structured PMP exam preparation course spends its scheduling work on the case where a schedule exists and nobody can use it.
Ask your own schedule a question this week: if the longest-lead item on your project arrived a fortnight late, what would move? If you can answer in five minutes with the tool open, the schedule is doing its job. If you would have to work it out on paper, the model is not the one being used to run the project.
Interested in going further?
The schedule people actually run a project from is often not the one in the system, and the gap between them is where surprises are stored. Omega’s PMP® Exam Preparation works through scheduling that stays usable through delivery.
Free study planner
Find out how ready you are for the PMP® exam
Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.
Want to prepare with a trainer? See our five-day live online PMP® course.
The concepts behind scheduling are introduced in the PMBOK® Guide Eighth Edition.
Ad · Amazon affiliate link.
References
A110: The PMBOK 8 Schedule Performance Domain: What It Really Covers
A114: Milestones vs Activities: Stop Treating Them as the Same Thing
A121: When a Schedule Baseline Needs to Change
A122: Tailoring Schedule Management for Adaptive Delivery
A120: Schedule Compression: Fast Tracking vs Crashing