Before any specification is written, somebody decides how the work will be divided into contracts and how the market will be approached. Those two decisions shape everything afterwards: where the gaps between suppliers fall, how much competition you get, how long the process takes, and who carries which risk. They are frequently taken for administrative convenience, by whoever is assembling the schedule of packages, and then lived with for years.
Appendix X4.4 of the PMBOK® Guide Eighth Edition covers procurement strategy, and the two questions worth spending real time on are packaging and market approach.
Packaging: how the work is divided
Fewer, larger packages move integration risk to a supplier. One contractor takes responsibility for a larger scope, the interfaces inside it are theirs to manage, and the buyer’s coordination effort falls. The costs are a higher price for carrying that risk, a smaller field of bidders who can take it on, and a considerable dependency on one organisation.
More, smaller packages keep control and the interfaces. The buyer gets a wider market, better prices on each package and the ability to replace a poor performer, and takes on the job of making the pieces meet. Every boundary between packages is an interface that somebody has to specify, coordinate and prove, and interfaces are where projects lose money.
Market approach
Open competition suits a capable market and a specifiable requirement. It gives the widest field and the best price discovery, and it costs time: advertising periods, larger evaluation effort, more bidders to handle. In regulated sectors it may be the default and the rules will say so.
Restricted competition or a framework suits a known market and a repeated need. A pre-qualified field shortens the process considerably and narrows it to organisations already assessed as capable. The risk is that the framework’s terms were written for a different kind of work, and using one because it is quick can commit you to a contract shape that does not fit.
Single source suits genuine uniqueness, and needs justifying in writing. A proprietary interface, an incumbent with knowledge nobody else can reconstruct, a safety case tied to one manufacturer. The record of why matters, both for audit and for the day somebody asks why the price has risen for the third consecutive year.
Two packages and a bridging plate
A defence programme integrated a new sensor system onto a platform, and divided the work into two contracts: one for the sensor and its mount, one for the platform modification. The split followed the organisation’s own budget structure, with the sensor bought from a capability budget and the modification from a platform support budget.
That was an administrative boundary rather than a technical one, and it fell in the worst available place: through the structural interface between the mount and the platform. Two suppliers, each with a specification written by a different team, each correct within its own scope.
The mismatch was about eleven millimetres and a difference in bolt pattern. It appeared at first integration, and neither supplier was contractually wrong, so neither was obliged to fix it. The resolution was a fabricated bridging plate, designed and qualified by the programme’s own engineering team, bolted across the joint with fresh paint and unweathered bolt heads standing out against the older finish either side.
The plate cost about seven weeks of programme time and a qualification exercise nobody had budgeted for. The underlying decision, which package boundary to use, had been taken in a budget meeting in about four minutes, by people who had no reason to think it was an engineering question.
The programme’s next procurement strategy carried a one-page interface analysis: where the package boundaries fall, what crosses each one, and who owns proving it. It moved one boundary and added a named integration authority to another, and neither change cost anything at the point it was made.
Engaging the market first
Ask the market before deciding. A short information exercise tells you what capability exists, how suppliers would prefer the work packaged, and what they will not bid for. Suppliers are usually candid about this, because a badly packaged tender costs them money too.
Check the timetable against the market’s calendar. Contractors and specialists commit their capacity months ahead, and a tender issued during a busy period gets fewer and worse responses. This is knowable in advance with one conversation, and it is the sort of thing a procurement strategy should record.
For a PMP® candidate, it helps to recognise that packaging and market approach are decisions with technical consequences, so a scenario about a gap between two suppliers is worth tracing back to where the contract boundary was drawn. A response that manages the dispute leaves the boundary in place for the rest of the work. Situations where each supplier is compliant and the work between them belongs to nobody are a standing feature of a structured PMP exam preparation course.
Before the next package goes out, draw the boundaries and list what crosses each one. Anything crossing a boundary needs a named owner for proving it works, and if you cannot name that person today, the interface is already a claim waiting to happen.
Interested in going further?
Package boundaries are drawn early, quickly and often for budgetary reasons, and the project lives with them for years. Omega’s PMP® Exam Preparation works through procurement strategy as a technical decision as much as a commercial one.
Free study planner
Find out how ready you are for the PMP® exam
Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.
Want to prepare with a trainer? See our five-day live online PMP® course.
Procurement strategy is set out in the appendices of the PMBOK® Guide Eighth Edition.
Ad · Amazon affiliate link.
References
A245: Make or Buy? How to Decide Before Procurement Begins
A247: RFP vs RFQ vs IFB vs ITT: Which Procurement Document Should You Use?
A248: Choosing a Supplier: Cheapest Is Not the Same as Best
A249: Fixed-Price vs Cost-Reimbursable vs Time-and-Materials Contracts
A250: Outcome-Based Contracts: Buying Results Rather Than Activity
PMP and PMBOK are registered marks of the Project Management Institute, Inc.