Schedule Compression: Fast Tracking vs Crashing

Schedule Compression: Fast Tracking vs Crashing

Somebody senior asks for six weeks back. There are only two ways to get them without changing what is being delivered, and each one buys time with a different currency: overlap work that was planned to happen in sequence, or put more resource onto it. Both are legitimate, both are limited, and the difference between a compression that works and one that unravels is usually whether anybody named the currency out loud.

Section 2.3 of the PMBOK® Guide Eighth Edition covers the schedule work these belong to, and the practical starting point is that neither technique is free and neither is unlimited.

What each one trades

Fast tracking pays in rework risk. Activities planned in sequence are started in parallel: detailed design begins before the concept is signed off, procurement starts before the specification is final, testing begins on a partially built system. Time comes back immediately, and the cost arrives later if the earlier activity changes anything the later one assumed. It costs no money at the point of decision, which is precisely why it is chosen under pressure, and why its consequences are so often a surprise.

Crashing pays in cash. More people, overtime, an additional shift, a supplier expedite fee. The duration of an activity shortens, the cost of it rises, and unlike fast tracking, you find out the price at the time. Crashing suits work that genuinely divides between people, which is a smaller set than most plans assume.

Where each stops working

Overlap risk rises faster than the time saved. Starting the second activity when the first is eighty per cent settled is usually sensible; starting it at thirty per cent is gambling most of its output. The relationship is not linear, and the practical discipline is to ask what proportion of the later work would have to be redone if the earlier activity changed in its remaining part.

Added people cost time before they save it. Somebody who already knows the work has to stop doing it in order to explain it, and on knowledge work the break-even point can be several weeks out. Crashing an activity that finishes in three weeks by adding two people to it will usually make it finish later, and this is the most reliably ignored fact in schedule recovery.

Compressing anything off the critical path buys nothing. It is possible to spend a considerable amount of money making non-critical work finish earlier, and every day of it is wasted. This sounds obvious and it happens constantly, because the activities people can see are not always the ones governing the date.

A transition compressed by both at once

A shared services centre was taking on finance processes from a business that was being divested, with a hard date set by the sale agreement. Six weeks into a thirty-week programme, the transition was four weeks behind because access to the seller’s systems had taken longer than anybody expected.

Both techniques were applied together. Knowledge transfer was overlapped with parallel running rather than completed first, which was the fast track. And the transition team was increased from nine to fourteen, which was the crash.

The crash cost about nine weeks of productivity before it produced any. Five new people needed briefing on a set of processes that only existed in the heads of the nine, and the briefing came out of the same nine people’s time. By week fourteen the team was genuinely faster; by week nine it had been slower, and the programme reported a further slip in the middle of the recovery, which is a difficult conversation nobody had prepared for.

The fast track worked better, with one expensive exception. Overlapping knowledge transfer and parallel running was fine for the eleven simpler processes. On the three complex ones, parallel running started before the transfer had covered the exception handling, and every exception encountered during parallel running had to be worked twice: once by the receiving team, wrongly, and once again with the seller’s specialist. That was about three weeks of waste concentrated in two processes.

The programme hit its date. What it took away was a rule: overlap only where the earlier activity is substantially settled, and never on the items where the knowledge is thinnest, which are exactly the ones where the pressure to overlap is greatest.

Deciding and recording

Name the currency in front of the person asking. Six weeks can be bought with about this much money, or with this much rework exposure on these specific activities. A sponsor presented with that choice usually makes a reasonable one; a sponsor who is simply told the date will be met has accepted a risk they were never shown.

Write the compression down as a decision with its assumptions. What was overlapped, what has to stay stable for the overlap to hold, and what the trigger is for stopping. When the earlier activity does change, that record turns an argument about blame into a planned response, which is the whole value of having written it.

For a PMP® candidate, the point to hold is that the two techniques buy time with different currencies, so a scenario asking how to recover a date is asking which risk the organisation is willing to carry. A response that adds people to a short activity late in its life will make the position worse. A structured PMP exam preparation course works through situations where a date must be recovered and both options have real costs.

Under pressure, write the two sentences before the meeting. Crashing this costs this much and shortens the path by this many days. Fast tracking these two activities saves this many days and puts this specific work at risk of being redone. Walking into a recovery conversation with those numbers changes who is making the decision.

By Andre Malowney

Interested in going further?

Recovering a date is the most common pressure in delivery and the one where the costs are least visible at the moment of choosing. Omega’s PMP® Exam Preparation works through compression decisions with the trade made explicit.

Free study planner

Find out how ready you are for the PMP® exam

Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.

Want to prepare with a trainer? See our five-day live online PMP® course.

Schedule compression and the techniques behind it are covered in the PMBOK® Guide Eighth Edition.

Ad · Amazon affiliate link.

References

A110: The PMBOK 8 Schedule Performance Domain: What It Really Covers
A121: When a Schedule Baseline Needs to Change
A117: Velocity: Useful Planning Aid or Dangerous Target?
A113: Float Explained: How Much Delay Can You Really Absorb?
A115: Agile Estimating vs Predictive Estimating

PMP and PMBOK are registered marks of the Project Management Institute, Inc.

Flyer for Enlighten Publications inviting readers to join their Early Reader List for access to nonfiction on psychology, work, culture, technology, and modern life. Features a QR code to scan, website URL enlighten-publications.com/early-reader-list, and a man reading a book.