When a Schedule Baseline Needs to Change

When a Schedule Baseline Needs to Change

Re-baselining has a poor reputation, and it has earned some of it, because the most common reason for doing it is that the variance has become embarrassing. That does not make it wrong in principle. A baseline exists to be measured against, and a baseline describing work the project is no longer doing measures nothing useful either.

Section 2.3 of the PMBOK® Guide Eighth Edition covers the schedule work this sits inside, and the distinction between a legitimate reset and a cosmetic one is about what has changed in the world.

Three situations that justify it

An approved scope change large enough to alter the plan. Where the work itself has changed by decision, continuing to measure against a plan for different work produces variance that describes the decision rather than performance. The reset follows the change approval and should be part of the same paper.

An external event outside the project’s control. A regulatory decision that moves, a sanction that stops work for a quarter, a supplier failure that resets a procurement, a site that becomes inaccessible. The test is that a competent project could not have prevented it and cannot recover it inside the existing plan.

A structural replan after the plan has been overtaken. Sometimes a project’s sequence has changed so comprehensively, through a combination of legitimate causes, that the baseline no longer describes the route being taken. Continuing to report against it produces numbers nobody can interpret, and a formal replan with an explicit decision is more honest than measuring against a fiction.

Two that do not

Performance variance. The work is taking longer because it is harder, the estimates were optimistic, or productivity is below assumption. This is precisely what the baseline exists to reveal, and resetting it removes the only record of it. The forecast should move; the baseline should not.

Reporting discomfort. A variance that is difficult to explain to a board is not a reason to change what it is measured against. Boards that discover this has happened lose confidence in everything else the project reports, which costs more than the uncomfortable conversation would have.

A test programme reset around a customer change

An aerospace programme was running structural qualification on a new component. Six months in, the customer changed the load case requirement, adding a regime that had not been part of the original specification, and the change was approved and funded through the proper route.

The physical effect was substantial. The test article had to be part stripped, its instrumentation removed and coiled onto a trolley, a new load frame assembled alongside, and the previous fixtures crated and labelled against the bay wall in case the original regime was needed again.

The schedule effect was proportionate. About fourteen weeks of new work, a resequencing of the remaining tests, and a different order of instrumentation fits. Measuring what followed against the original baseline would have produced a variance of several months that described the customer’s decision and nothing about how the programme was performing.

The reset was done as part of the change approval, in one paper: what changed, why, the new baseline, and the original retained for reference with the performance record up to the change preserved. Two things came out of that discipline. The programme could still say how it had performed in its first six months, which mattered when the same customer asked about capability. And when a second change was proposed four months later, the comparison between the two baselines made the cumulative effect visible immediately.

Doing it properly

Get it approved by whoever approved the original. A baseline reset is a governance act, and a project that resets its own reference point has removed somebody else’s ability to hold it to anything.

Record what changed and why, in a form somebody can read in two years. One paragraph: the cause, the date, what moved, and who approved it. Without this, a project with three resets is indistinguishable from a project that was repeatedly late.

Keep the original and the performance to date. The old baseline goes into the record rather than the bin, with the variance up to the reset preserved. This is what allows an organisation to learn anything about its estimating, and it is the first thing lost when a reset is done by overwriting a file.

For a PMP® candidate, the thing to carry is that a reset is justified by a change in the work or its circumstances, so a scenario proposing a re-baseline is asking what has actually changed. A response that resets after a run of poor performance has removed the measurement. Situations where a reset is genuinely warranted and has to be argued for are a regular feature of a structured PMP exam preparation course.

Where a reset is being discussed, write the one-paragraph justification first and read it aloud. If it describes something that happened to the project, the case is sound. If it describes how the numbers look, the conversation that is needed is a different one.

By Andre Malowney

Interested in going further?

Resetting a baseline is legitimate, consequential and easy to do for the wrong reason at the wrong moment. Omega’s PMP® Exam Preparation works through replanning as a governed decision.

Free study planner

Find out how ready you are for the PMP® exam

Our free PMP® Exam Readiness & Study Planner checks your likely eligibility route, shows the areas that need most attention and builds a week-by-week study plan around the time you have. It takes about 3 minutes.

Want to prepare with a trainer? See our five-day live online PMP® course.

Baselines, replanning and schedule control are covered in the PMBOK® Guide Eighth Edition.

Ad · Amazon affiliate link.

References

A110: The PMBOK 8 Schedule Performance Domain: What It Really Covers
A120: Schedule Compression: Fast Tracking vs Crashing
A122: Tailoring Schedule Management for Adaptive Delivery
A117: Velocity: Useful Planning Aid or Dangerous Target?
A113: Float Explained: How Much Delay Can You Really Absorb?

PMP and PMBOK are registered marks of the Project Management Institute, Inc.

Flyer for Enlighten Publications inviting readers to join their Early Reader List for access to nonfiction on psychology, work, culture, technology, and modern life. Features a QR code to scan, website URL enlighten-publications.com/early-reader-list, and a man reading a book.